ASME reissues its boiler and vessel code every two years. Your report names one edition.
The 2025 edition of the ASME Boiler and Pressure Vessel Code is the latest. Section V says how to examine, the referencing code says what passes, and the report has to name the edition of each.
Key takeaways
- Section V says how to examine. The referencing code says what passes.
- The edition comes from the referencing code and the construction contract, not from the template.
- Check the referencing code, with its division and edition.
One wrong-code story from customer calls is the wrong ASME section for boiler piping. The tech knows the method. What goes wrong is the code behind it: Section V says how to examine, and the boiler, vessel, or piping code decides what passes.
Getting the section right is the first job on an ASME report. Getting the edition right is the second, and it comes around every two years.
A two-year cycle
ASME reissues the Boiler and Pressure Vessel Code every two years. The 2025 edition is the latest, and it's the edition our Library pages for Section V, Section VIII, and Section IX are written to.
Which edition applies on a job is the one the referencing code and the construction contract name. States, provinces, and cities that adopt the code bring Section V in with it, through the construction sections that reference it, and authorized inspectors check examinations against it.
So a new edition on the shelf doesn't change the job in front of you. The contract does. The risk is the other way round: a template that was set up for one edition and never updated when the contracts moved on.
Two codes on every examination report
Section V is a methods book. Each article sets the requirements for one examination method: the written procedure, the equipment, calibration, technique, and what the examination record has to show.
It doesn't decide whether a weld passes. Section V applies when another code calls for it, such as Section VIII for a pressure vessel, Section I for a boiler, or B31.3 for process piping, and that code sets the acceptance criteria. A report that cites Section V and nothing else can't be accepted, because Section V has no acceptance criteria for welds.
Section V is organized by article, one per method. Article 2 covers radiography, Article 4 ultrasonic examination of welds, Article 6 penetrant, Article 7 magnetic particle, and Article 9 visual. The report names the article it followed, so the reviewer knows which set of requirements the examination was held to. Subsection A holds ASME's own articles; Subsection B adopts ASTM standards, such as the wire IQI standard, under ASME's own designations.
Section V doesn't certify anyone either. The examiner is qualified to the referencing code, usually through SNT-TC-1A or CP-189, and the report carries the examiner's name, certification level, and signature, then the reviewer's sign-off.
That means an examination report carries at least two codes, and each has its own edition. B31.3 is a separate ASME code with its own edition. Our Library page is written to B31.3-2024, while the vessel and boiler sections sit on the two-year cycle.
A plant job shows why it matters. The vessel is built to Section VIII, the piping around it to B31.3, and both point at Section V for how to examine. The same crew can write reports to three editions in one day.
The procedure has a revision too
Every Section V examination runs to a written procedure, and some articles require that procedure to be demonstrated before it's used on production work. The report names the procedure number and its revision. Without them, the reviewer can't confirm the examination was valid.
The weld has its own paperwork behind it. Section IX covers how the welding procedure and the welder are qualified, and the report points at the welding procedure the weld was made to. One examination report can lean on four documents, each with a date or a revision: the referencing code, Section V, the written examination procedure, and the welding procedure.
What a reviewer checks first
Before any indication, a Level III reading an ASME examination report wants to see the referencing code, with its division and edition where it has them. Then the Section V edition and the article followed. Then the written procedure number and revision.
Then the details that depend on them. An IQI that doesn't match the material thickness makes the whole radiograph invalid, whatever it shows. On a Section VIII vessel, the report also names the division, and the joint category and type.
Every one of those is a field, and every one is easy to carry forward from the last job's report by accident. That's how copy-paste from an old report turns into a kickback.
None of this needs new software to get right. It needs the job to carry its codes and editions, and the report to show them every time. A checklist on the wall does part of it. A field the tech can't skip does more.
Where Weld Done fits
In Weld Done the job starts from your inspection plan, so its procedures come with it, and each RT, VT, and UT indication is checked against the acceptance limits as it's entered.
See how it works on the Standards logic page, or read why NDT service companies switch from Excel and PDF. The NDT reporting checklist has eight ways to get reports right the first time.
Author
Who wrote it.

See your own report rebuilt.
Book a 30-minute demo on one of your real reports.
Not ready to talk? The calculator works out hours and costs back from your own numbers.