ASME B31.3: process piping in plants and refineries.

The code for piping inside refineries, chemical plants, and process facilities: how it's designed, built, examined, and tested before it goes into service.

Process Piping · ASME · B31.3-2024

What it covers

ASME B31.3 in plain terms.

ASME B31.3 covers process piping from design to the pressure test. It stops at the plant fence: pipelines between facilities are B31.4 and B31.8, and piping already in service is inspected to API 570.

The code sorts piping by fluid service, and the fluid service sets how much examination the welds get. Normal fluid service gets random radiography or ultrasonic testing of a sample of welds; less hazardous service can be visual only; severe cyclic conditions get full volumetric examination.

Chapter VI holds examination and testing. It separates the owner's inspector, who checks the work on the owner's behalf, from the examiners, who perform the examinations for the manufacturer or erector.

B31.3 borrows its methods from Section V and its welding qualification from Section IX. The acceptance criteria are its own, set out in Chapter VI.

Where it’s used: Oil, gas, and petrochemical

In the glossary: Hydrostatic test

Regulation

OSHA's process safety management rule expects plants to follow recognized and generally accepted engineering practices, and B31.3 is the one for process piping. Some states and provinces adopt it in their pressure equipment rules.

Full title
Process Piping
Issued by
ASME
Current edition
B31.3-2024
Applies to
Piping in petroleum refineries, chemical, pharmaceutical, gas processing and similar plants
Required by
Owners' specifications, and the states and provinces that adopt it
Examination
Chapter VI: examination, inspection, and testing
Examination methods
ASME BPVC Section V
Welding qualification
ASME BPVC Section IX

Who it's for

One record. Both sides of the job.

How inspection works

Methods under ASME B31.3.

Who sets the procedure, who sets acceptance, and who may do the work, method by method.

MethodProcedureAcceptanceCertification
Visual (VT)ASME Section V Article 9B31.3 Chapter VI acceptance criteriaExaminer qualified to the employer's written practice
Radiographic (RT)ASME Section V Article 2B31.3 Chapter VI acceptance criteriaSNT-TC-1A or CP-189 Level II, plus radiation safety
Ultrasonic (UT)ASME Section V Article 4B31.3 Chapter VI acceptance criteria, or its ultrasonic alternativeSNT-TC-1A or CP-189 Level II
Magnetic particle (MT)ASME Section V Article 7B31.3 Chapter VI acceptance criteriaSNT-TC-1A or CP-189 Level II
Penetrant (PT)ASME Section V Article 6B31.3 Chapter VI acceptance criteriaSNT-TC-1A or CP-189 Level II

Acceptance criteria

How a weld passes or fails.

B31.3 sets acceptance in one table in Chapter VI, by imperfection and by fluid service. The same indication can be acceptable in normal service and rejectable under severe cyclic conditions.

  • Cracks reject in every service.
  • Lack of fusion and incomplete penetration are limited by depth and length, with tighter limits for severe cyclic service.
  • Internal porosity and slag are limited by size and distribution against the wall thickness.
  • Undercut, surface porosity, reinforcement, and root concavity have visual limits.
  • When a random sample finds a reject, B31.3 calls for progressive examination: more welds by the same welder or operator are examined, and the sample widens until the defects are bounded.

The owner can specify more examination than the code requires, and often does. The engineering design names the fluid service, and the report has to match it.

A summary, not the code. Limits and exceptions are in the edition your job works to.

The report

What ASME B31.3 reports have to carry.

The fields a Level III checks before signing. Miss one and the report comes back.

  • Project, unit, line number, isometric, and weld ID
  • Welder or operator ID and the welding procedure
  • Material, size, schedule, and fluid service category
  • B31.3 edition, and whether the weld was in the random sample or a progressive one
  • Method and technique per Section V; for RT, the IQI and sensitivity
  • Each indication: type, location, size, and the accept or reject call
  • Disposition, repairs, and the progressive examination that followed a reject
  • Examiner name, certification level and signature; owner's inspector acceptance

How Weld Done builds your NDT report template

  1. The wrong fluid service.

    A severe cyclic line examined and accepted as normal service passes welds the code would reject.

  2. A reject with no progressive trail.

    A random-sample reject needs the extra welds examined and recorded. Without them the lot isn't accepted.

  3. Section V as the acceptance standard.

    Section V says how to examine. The acceptance criteria come from B31.3, and the report has to cite them.

  4. In-service work to the construction code.

    Piping already in service is inspected to API 570. B31.3 is for new construction and repairs to its rules.

Related codes

The codes around it.

Edition referenced: B31.3-2024. All codes and standards

FAQ

Questions.

Every other answer is on the FAQ page.

Visit FAQ
How much examination does ASME B31.3 require?

It depends on the fluid service. Normal service gets random radiography or ultrasonic testing of a sample of welds plus visual examination; less hazardous service can be visual only; severe cyclic conditions get full volumetric examination. The owner can require more.

What is progressive examination in B31.3?

When a weld from a random sample is rejected, more welds by the same welder or operator are examined. If those fail too, the sample widens until the defective work is bounded and repaired.

Where are the B31.3 acceptance criteria?

In Chapter VI, in one table organized by imperfection and fluid service. Section V supplies the examination methods, not the acceptance criteria.

Does B31.3 cover piping already in service?

No. In-service inspection of process piping is API 570. B31.3 covers new construction and the rules repairs must meet.